State Road 3 to see restrictions north of Greensburg

The Indiana Department of Transportation plans to close single lanes of State Road 3 Tuesday and Wednesday as the north-south highway approaches its overpass at Interstate 74 on the north side of Greensburg. INDOT says that crews hope to take advantage of good weather to remove temporary asphalt pavement placed as median crossovers during last year’s construction of the twin bridges.

INDOT says that traffic flow will continue at the State Road 3 bridge site in each direction on single 10-foot lanes. There will be no ramp closures.

INDOT says that Milestone is the state’s contractor for this $3,748,040 project that replaced State Road 3 bridges with two new four-span concrete beam bridges. Some clean-up and landscaping will remain to be done after this week’s temporary pavement removal.